Retreat Phase I is the first of the Anzera ‘Smart Homes’ series and is located on a small project site of half an acre, with subsequent phase II, III & IV located on 3 acres each on an overall 9 acre project site.

Work at the initial half-acre site is as follows

1.    Excavation works done with plots leveled according to the downward slope of the land.
2.    Road formation done plus metal work complete
3.    Plot demarcation done
4.    5 of 9 units sold
5.    Civil construction of 3 units completed and finishing works underway with expected handover by August end.
6.    Civil works another 2 units almost complete, with expected handover of villas by October end.